§ 17.22.110. Term of special permit.
Latest version.
Special permits granted under this chapter shall lapse within two years, excluding the time required to pursue or await the determination of an appeal from the grant thereof, if a substantial use has not commenced sooner or if construction has not started. The council may grant an extension, after a due process hearing, for good cause, and shall grant an extension if delay has been caused by the need to seek other permits.
(C.O.90-237 § 18 (part))