§ 8.28.070. Seismograph tests.  


Latest version.
  • A.

    The blasting contractor shall be required to place no less than two separate seismographs on the site at locations to be determined by the fire chief. Reports from the seismographs shall be submitted to the fire chief within twenty-four hours of any blast.

    B.

    In the event that any seismograph reading exceeds the limits set forth in 527 C.M.R. 13.00, or in the event any hazardous condition is noted or any injury occurs to persons or property, blasting operations shall be halted until such time and under such conditions determined by the fire chief.

(C.O.04-204 § 6)